JOID Milestone D Report **1. If you have code are features frozen? y/n/na ** n- as we are waiting for collaborative projects like ONOS to provide JOID integration. We expect this to happen mid of December. **2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? y/n/na ** y - all MAAS and Juju interfaces planned for release B are frozen. **3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite) y/n/na ** n/a **4. If you require post-install processing have you consulted with CI (Octopus), CD (Releng), and/or companion test projects (functest, yardstick, etc) regarding scripts you may need to provide such as for install, set-env, run-test, clean-env? ** n/a **5. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? y/n/na ** n/a (we have code) **6. List/describe your progress to date? ** Please refer to JIRA dashboard for JOID: https://jira.opnfv.org/secure/Dashboard.jspa?selectPageId=10614 **7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) ** Remaining work here: https://jira.opnfv.org/browse/JOID-21?filter=10666 **8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red ** Yellow - as there are dependencies on other projects **9. List any serious or blocking issues that are impeding progress on your project:** Genesis is still working on defining the baseline requirements for installers