JIRA: IPVSIX-10 Create timeline of milestones of IPv6, and aligned with B release
08/18/2015: B Release Milestone A
08/18/2015: B Release Milestone B
09/25/2015: B Release Milestone C
09/25: Revised PoC 1 Diagram completion
10/09: Gap analysis with ODL completion
10/15: Test Plan completion
10/30: Decision on Snapshot image or Metadata (latency issue)
11/15: Jenkins integration completion
11/30: Test completion
12/01/2015: B Release Milestone D
01/05/2016: B Release Milestone E
02/02/2016: B Release Target Date