JIRA: IPVSIX-10 Create timeline of milestones of IPv6, and aligned with B release
08/18/2015: B Release Milestone A
08/18/2015: B Release Milestone B
09/25/2015: B Release Milestone C
09/25: Revised PoC 1 Diagram completion
10/09: Sprint C-1: Gap analysis with ODL completion (IPVSIX-18)
10/15: Sprint C-2: Test Plan completion (IPVSIX-14)
10/30: Decision on Snapshot image or Metadata (latency issue)
11/15: Sprint C-3: Jenkins integration completion (IPVSIX-7)
11/30: Sprint C-4: Test completion (IPVSIX-27)
12/01/2015: B Release Milestone D
01/05/2016: B Release Milestone E
02/02/2016: B Release Target Date