1.Project name: OpenContrail Virtual Networking for OPNFV aka OVNO
2.Project status indicator for milestone C readiness: Green
3.Name of person providing status: Stuart Mackie
4.a link to your Jira tasks (filtered on R2): https://jira.opnfv.org/issues/?jql=project%20%3D%20OVNO
5.a link to your Jira dashboard: https://jira.opnfv.org/browse/OVNO/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel
6.a statement of your progress at linking cross project dependencies in Jira: Links to Genesis, Fuel, Apex, JOID. Compass4nfv being investigated.
7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile): OpenContrail is already supported in Fuel and JOID, plus Puppet scripts exist. Will line up with installer development cycles.
8.a statement of your readiness (high level planning complete & in Jira) for future sprints: High level tasks in Jira
9.a statement about any issues you have: None yet
10. How & when you will finish getting your tasks & dependencies into Jira if not complete: Complete except for Compass
11.how and when you will get ready to start development for Brahmaputra if not ready now: Ready
12.a statement summarizing your project risk analysis & planning status. Milestone-C: Ready