+ | 1. Project name ARMBand | ||
+ | |||
+ | 2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
+ | Green | ||
+ | |||
+ | 3.Name of person providing status | ||
+ | Bob Monkman | ||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2) | ||
+ | https://jira.opnfv.org/issues/?jql=project%20%3D%20ARMBAND%20AND%20labels%20%3D%20R2 | ||
+ | |||
+ | 5. a link to your Jira dashboard | ||
+ | https://jira.opnfv.org/browse/ARMBAND/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel | ||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira | ||
+ | We have given our input to tests, Fuel installer, as well as CI/Jenkins integration. | ||
+ | Dependency on CI is created (OCTO-136) and linked by ARMBAND-17. | ||
+ | Dependency on Fuel is created (FUEL-39) and linked by ARMBAND-11. | ||
+ | Dependency on test is created (YARDSTICK-154) and linked by ARMBAND-15. | ||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
+ | We have our story done for Sprint C-1 (ARMBAND-2). | ||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
+ | All epics are identified and created in Jira (ARMBAND-1,5,7,9,11,14,17 and 20). | ||
+ | Stories are also planned (ARMBAND-2,3,4,6,8,10,12,13,15,16,18 and 19). | ||
+ | |||
+ | 9.a statement about any issues you have | ||
+ | No current issues. | ||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
+ | We believe that those are complete. | ||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now | ||
+ | We are starting now (ARMBAND-2). | ||
+ | |||
+ | 12.a statement summarizing your project risk analysis & planning status | ||
+ | Low risk and on track. | ||