This shows you the differences between two versions of the page.
| — |
bottlenecks_milestone_c_report [2015/09/28 20:40] (current) Debra Scott created |
||
|---|---|---|---|
| Line 1: | Line 1: | ||
| + | 1. Project name | ||
| + | Bottlenecks | ||
| + | |||
| + | 2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
| + | Green | ||
| + | |||
| + | 3.Name of person providing status | ||
| + | Hongbo Tian | ||
| + | |||
| + | 4.a link to your Jira tasks (filtered on R2) | ||
| + | https://jira.opnfv.org/browse/BOTTLENECK-20?jql=project%20%3D%20BOTTLENECK%20AND%20labels%20%3D%20R2 | ||
| + | |||
| + | 5.a link to your Jira dashboard | ||
| + | https://jira.opnfv.org/browse/BOTTLENECK/?selectedTab=com.atlassian.jira.jira-projects-plugin:issues-panel | ||
| + | |||
| + | 6.a statement of your progress at linking cross project dependencies in Jira | ||
| + | Bottlenecks is dependent on CI,since one of our committers is the committer of CI. He is working on cooperation between bottlenecks and CI and almost finished most work。 | ||
| + | |||
| + | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
| + | We have identified Jira tasks and developed the codes for bottlenecks. And | ||
| + | We have upload some codes into gerrit. | ||
| + | |||
| + | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
| + | We are planning 3 Sprints: | ||
| + | Sprint 1: bottlenecks framwork and test cases design(finished) | ||
| + | Sprint 2: test tools and first testcase coding(ongoing), since the testcase can cover many scenarios, it will take days for coding. | ||
| + | Sprint 3: system bottlenecks analysis and first test case scalability. Bottlenecks documents | ||
| + | |||
| + | 9.a statement about any issues you have | ||
| + | None yet | ||
| + | |||
| + | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
| + | Jira is complete for Sprint 1 and 2. Design has been finished and we are working on coding. | ||
| + | |||
| + | 11.how and when you will get ready to start development for Brahmaputra if not ready now | ||
| + | We are coding for bottlenecks. | ||
| + | |||
| + | 12.a statement summarizing your project risk analysis & planning status | ||
| + | Low risk and on track so far. | ||