+ | 1. Project name | ||
+ | Compass4nfv | ||
+ | |||
+ | 2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
+ | Green | ||
+ | |||
+ | 3.Name of person providing status | ||
+ | Weidong Shao, with assistance from Chen Shuai, and Chi Gang(Justin) | ||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2) | ||
+ | https://jira.opnfv.org/issues/?jql=project%20%3D%20COMPASS%26labels%3DR2 | ||
+ | |||
+ | 5.a link to your Jira dashboard | ||
+ | https://jira.opnfv.org/browse/COMPASS/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel | ||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira | ||
+ | Compass4nfv is an installer project under Genesis. Currently working with other Genesis committers on Jira reviews. | ||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
+ | Not an agile mode, but the next major milestone in 10/30 for support of deploying OpenStack Liberty, and for supporting installation of Compass on a vanilla OS host (in addition to ISO-based install) | ||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
+ | Will work with Genesis, and other projects that have requirements on Genesis. There are certain uncertainties in this area as the Genesis requirements are still under review. | ||
+ | |||
+ | 9.a statement about any issues you have | ||
+ | There are some risks in the cross-project dependencies, due to the nature of installer, with support of many different upstream projects. | ||
+ | |||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
+ | Will map new approved Genesis to our Jira as they come up. | ||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now | ||
+ | We are already in active development and have a working foundation (that supports OpenStack kilo/ODL lithium and ONOS Drake) | ||
+ | |||
+ | 12.a statement summarizing your project risk analysis & planning status | ||
+ | Risk is low. Overall status is Green. | ||