User Tools

Site Tools


copper_milestone_c_report

This is an old revision of the document!


1. Project name Copper

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues Green

3.Name of person providing status Bryan Sullivan

4.a link to your Jira tasks (filtered on R2) Copper R2 Jira tasks

5.a link to your Jira dashboard Copper Jira Dashboard

6.a statement of your progress at linking cross project dependencies in Jira Complete: see Genesis-54, Functest input

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) First development cycle is underway.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints We do not plan to organize around sprints.

9.a statement about any issues you have Complexity of getting lab resources; steep/long learning curve on fundamentals of creating workloads and virtual network environments under OpenStack and OpenDaylight;

10.how & when you will finish getting your tasks & dependencies into Jira if not complete Jira is complete.

11.how and when you will get ready to start development for Brahmaputra if not ready now Development for Brahmaputra is underway.

12.a statement summarizing your project risk analysis & planning status Detailed risk management planning has not been attempted. Overall nature or risks and dependencies is clear, e.g. see issues above. No obvious solutions to these issues other than additional resources. We will do our best.

copper_milestone_c_report.1443473134.txt.gz · Last modified: 2015/09/28 20:45 by Debra Scott