doctor_milestone_c_report

1.Project name: Doctor

2.Project status indicator for milestone C readiness: Green

3.Name of person providing status: Ryota Mibu

4.a link to your Jira tasks (filtered on R2): https://jira.opnfv.org/issues/?jql=project%20%3D%20DOCTOR%20AND%20labels%20%3D%20R2

5.a link to your Jira dashboard: https://jira.opnfv.org/browse/DOCTOR

6.a statement of your progress at linking cross project dependencies in Jira: Cross project tasks are created in both side of projects and linked (DOCTOR-21, 22).

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile): All tasks, related to OPFNV B release, are tagged with 'R2' and set deadlines.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints: All epics are identified and created in Jira (DOCTOR-32, 34 and 35).

9.a statement about any issues you have: No current issue

10.how & when you will finish getting your tasks & dependencies into Jira if not complete: (We believe that those are complete.)

11.how and when you will get ready to start development for Brahmaputra if not ready now: (If more detailed planning are required in milestone-C, we can start the elaboration in task DOCTOR-31.)

12.a statement summarizing your project risk analysis & planning status: Low risk and on track

doctor_milestone_c_report.txt · Last modified: 2015/09/28 20:48 by Debra Scott