We plan for three work-packages until Brahmaputra code-freeze (Milestone E) Jan 5 - 2016
Goal:
Content:
Definition of done:
Passing build-, automated deploy- and manual smoke-test.
Due dates:
Goal: * Collaboration/integration project freeze - no more OPNFV integration projects than those integrated at this time will be integrated with Fuel@OPNFV Brahmaputra release.
* Plugins/integration projects are required to be based on Kilo/Fuel 7.0. Fuel 7.0/Kilo is merged to master and the experimental branch will be used for Fuel 8.0/Liberty rebasing.
Rebasement of Fuel@OPNFV core to Kilo and Fuel 7.0 (Experimental branch), including build, deploy, test, OPNFV CI-pipeline, Fuel@OPNFV Developers' CI-pipeline…
Definition of done: Passing build-, install- and partial devel-pipeline func-test.
Due date: Dec 11 - 2015
Content: TBD
Definition of done: Passing build-, install- and partial devel-pipeline func-test.
Due date: Jan 5 - 2016
Content: Project release consolidation
Definition of done: Stabilization, documentation, bare-metal ci-pipeline clean-out, any PR-material, etc.
Due date: Feb 2 - 2016