Fuel@OPNFV Brahmaputra work-package planning

We plan for three work-packages until Brahmaputra code-freeze (Milestone E) Jan 5 - 2016

Work-package 1

Goal:

  • Rebasement of Fuel@OPNFV core to Kilo and Fuel 7.0 (Experimental branch), including build, deploy, test, OPNFV CI-pipeline, Fuel@OPNFV Developers' CI-pipeline…
  • First integration of Brahmaputra integration/collaboration projects (Fuel plug-ins). Goal is to get 4 projects onboard for WP1. Target system state for the integration is Juno and Fuel 6.1 (master branch)
  • Auto deploy of integrated projects.
  • Func-test/Yardstick real or noop verification of integrated projects.

Content:

Work-package 1

Definition of done:

Passing build-, automated deploy- and manual smoke-test.

Due dates:

  • Latest date for integrated projects to sign-up for WP1: Thu November 5 -15
  • Latest date for a partially functional plugin commit: Tue Nov 10 -15
  • Latest date for a partially functional plugin demo (Yoytube clip or otherwise): Fri Nov 15

Work-package 2

Goal: * Collaboration/integration project freeze - no more OPNFV integration projects than those integrated at this time will be integrated with Fuel@OPNFV Brahmaputra release.

* Plugins/integration projects are required to be based on Kilo/Fuel 7.0. Fuel 7.0/Kilo is merged to master and the experimental branch will be used for Fuel 8.0/Liberty rebasing.

Rebasement of Fuel@OPNFV core to Kilo and Fuel 7.0 (Experimental branch), including build, deploy, test, OPNFV CI-pipeline, Fuel@OPNFV Developers' CI-pipeline…

  • First integration of Brahmaputra integration/collaboration projects (Fuel plug-ins). Goal is to get 4 projects onboard for WP1. Target system state for the integration is Juno and Fuel 6.1 (master branch)
  • Auto deploy of integrated projects.
  • Func-test/Yardstick real or noop verification of integrated projects.

Definition of done: Passing build-, install- and partial devel-pipeline func-test.

Due date: Dec 11 - 2015

Work-package 3

Content: TBD

Definition of done: Passing build-, install- and partial devel-pipeline func-test.

Due date: Jan 5 - 2016

Consolidation

Content: Project release consolidation

Definition of done: Stabilization, documentation, bare-metal ci-pipeline clean-out, any PR-material, etc.

Due date: Feb 2 - 2016