Fuel@OPNFV Brahmaputra work-package planning
We plan for three work-packages until Brahmaputra code-freeze (Milestone E) Jan 5 - 2016
Work-package 1
Goal:
Rebasement of Fuel@OPNFV core to Kilo and Fuel 7.0 (Experimental branch), including build, deploy, test, OPNFV CI-pipeline, Fuel@OPNFV Developers' CI-pipeline…
First integration of Brahmaputra integration/collaboration projects (Fuel plug-ins). Goal is to get 4 projects onboard for WP1. Target system state for the integration is Juno and Fuel 6.1 (master branch)
Auto deploy of integrated projects.
Func-test/Yardstick real or noop verification of integrated projects.
Content:
Work-package 1
Definition of done:
Passing build-, automated deploy- and manual smoke-test.
Due dates:
Latest date for integrated projects to sign-up for WP1: Thu November 5 -15
Latest date for a partially functional plugin commit: Tue Nov 10 -15
Latest date for a partially functional plugin demo (Yoytube clip or otherwise): Fri Nov 13 -15
Work-package 2
Goal:
Collaboration/integration project freeze - no more OPNFV integration projects than those integrated at this time will be integrated with Fuel@OPNFV Brahmaputra release - unless they come with upstream project integration in WP3.
Plugins/integration projects are required to be (re)based on Kilo/Fuel 7.0.
Fuel 7.0/Kilo is merged to master and the experimental branch will be used for Fuel 8.0/Liberty rebasing.
Content:
-
Definition of done:
Passing build-, automated deploy- and manual smoke-test.
Due dates:
Latest date for integrated projects to sign-up for Fuel@OPNFV WP2/Brahmaputra: Fri November 13 -15
Latest date for a functional plugin commit based on Fuel 7/Kilo: Thu Dec 10 -15
Latest date for a functional plugin demo (Yoytube clip or otherwise): Fri Dec 17 -15
Work-package 3
Goal:
Content:
TBD
Definition of done:
Passing build-, install- and partial func-test.
Due date: Jan 5 - 2016
Consolidation
Content:
Project release consolidation
Definition of done: Stabilization, documentation, bare-metal ci-pipeline clean-out, any PR-material, etc.
Due date: Feb 2 - 2016