Task | Deliverable details | Status (per Apr/2/2015) |
---|---|---|
Target system state fully defined and frozen | Target System State agreed on Apr/1 | green |
Common components (puppet manifests) for "OPNFV-INSTALLATION and MAINTENANCE" phase available in "common" directory | Several contributions still in Gerrit review | yellow |
Task | Deliverable details | Status (per Apr/2/2015) |
---|---|---|
Code complete (common components frozen, all functionality in place - "OPNFV-INSTALLATION and MAINTENANCE" phase) | * Common Puppet manifests available in genesis repo * Changes for HA in Gerrit review: 240, 242, 245, 246 | yellow |
Scripts for automatic build of a bootable disk ISO image | Foreman approach: * Build scripts available in genesis repo: Foreman build Log of successful build on Apr/2 build metadata foreman ISO image Fuel approach: * Build scripts available in genesis repo: Fuel build Log of successful build on Apr/2 build metadata Fuel ISO | green |
Task | Deliverable details | Status |
---|---|---|
Automatic build and install on LF hardware PODs | Status on Apr/9: Issues which were pending from RC0 resolved (HA deployment, Ceph deployment) Because LF hardware not yet available to project teams, "deploy to LF HW" pending Fuel and Foreman deployment approaches both have build scripts available (non operational yet) | yellow to red |
Tempest and Robot test frameworks available on LF hardware |
Task | Deliverable details | Status |
---|---|---|
Automatic testing on LF hardware fully functional (FuncTest supplied tests; test infra (tempest, robot) setup independently from installer) |
Task | Deliverable details | Status |
---|---|---|
final release cut |
Task | Deliverable details | Status |
---|---|---|
Bootable disk image(s) (ISO) available | ||
Documentation (user guide) available | ||
Documentation (test scenarios that release complies with) available | (FuncTest supplied | |
Documentation (hardware guide - Pharos supplied) available | (Pharos supplied) |
Official release
Milestone | Date | Deliverable |
---|---|---|
M1 | 02/15/2015 | Hardware ordered, BGS components chosen |
M2 | 02/28/2015 | Base installer completed (Foreman/Quickstack and Fuel approach) automated ODL - O/S installation (both approaches) |
M3 | 03/15/2015 | Installation to OPNFV hardware, integration with CI/Jenkins |
M4 | 03/31/2015 | Tempest / Robot scenario tests available and automatically triggered by CI/Jenkins. Feature set frozen |
See also BGS Etherpad for the most recent information on project plan status.