This is an old revision of the document!
NOTE: Details below are outdated and not maintained any more. Please refer to the link above for latest status.
Task | Deliverable details | Status (per Apr/2/2015) |
---|---|---|
Target system state fully defined and frozen | Target System State agreed on Apr/1 | green |
Common components (puppet manifests) for "OPNFV-INSTALLATION and MAINTENANCE" phase available in "common" directory | Several contributions still in Gerrit review | yellow |
Task | Deliverable details | Status (per Apr/2/2015) |
---|---|---|
Code complete (common components frozen, all functionality in place - "OPNFV-INSTALLATION and MAINTENANCE" phase) | * Common Puppet manifests available in genesis repo * Changes for HA in Gerrit review: 240, 242, 245, 246 | yellow |
Scripts for automatic build of a bootable disk ISO image | Foreman approach: * Build scripts available in genesis repo: Foreman build Log of successful build on Apr/2 build metadata foreman ISO image Fuel approach: * Build scripts available in genesis repo: Fuel build Log of successful build on Apr/2 build metadata Fuel ISO | green |
Task | Deliverable details | Status |
---|---|---|
Automatic build and install on LF hardware PODs | Status on Apr/9: * Issues which were pending from RC0 resolved (HA deployment, Ceph deployment) * Because LF hardware not yet available to project teams, "deploy to LF HW" pending * Fuel and Foreman deployment approaches both have build scripts available (non operational yet) | yellow to red |
Tempest and Robot test frameworks available on LF hardware |
Task | Deliverable details | Status |
---|---|---|
Automatic testing on LF hardware fully functional (FuncTest supplied tests; test infra (tempest, robot) setup independently from installer) |
Task | Deliverable details | Status |
---|---|---|
final release cut |
Task | Deliverable details | Status |
---|---|---|
Bootable disk image(s) (ISO) available | ||
Documentation (user guide) available | ||
Documentation (test scenarios that release complies with) available | (FuncTest supplied | |
Documentation (hardware guide - Pharos supplied) available | (Pharos supplied) |
Official release
Milestone | Date | Deliverable |
---|---|---|
M1 | 02/15/2015 | Hardware ordered, BGS components chosen |
M2 | 02/28/2015 | Base installer completed (Foreman/Quickstack and Fuel approach) automated ODL - O/S installation (both approaches) |
M3 | 03/15/2015 | Installation to OPNFV hardware, integration with CI/Jenkins |
M4 | 03/31/2015 | Tempest / Robot scenario tests available and automatically triggered by CI/Jenkins. Feature set frozen |
See also BGS Etherpad for the most recent information on project plan status.