This page provides an outline of the options available for establishing a CI and development environment for OPNFV. The infrastrcuture required can be evaluated in terms of the baseline deployment POD's needed to support OPNFV activities. Each POD is assumed to be made up of:
3 x Control node (for HA/clustered setup of OpenStack and OpenDaylight) 2 x Compute node (to bring up/run VNFs) 1 x Jump Server/Landing Server in which the installer runs in a VM (FUEL/TripleO/Oscar)
Acquisition cost - Approx 200K USD
Lead Time to operation -
Power Needs - 10KW (over 2 racks)
Running costs -
Acquisition cost - Approx 200K USD
Lead Time to operation -
Power Needs - 10KW (over 2 racks)
Running costs -
Acquisition cost - 0
Lead Time to operation -
Power Needs - 0
Running costs - Approx 12K USD/month (first year)
Acquisition cost - 40-50K USD
Lead Time to operation -
Power Needs - >5KW (in one rack)
Running costs -
Acquisition cost - 40-50K USD
Lead Time to operation -
Power Needs - >5KW (in one rack)
Running costs -
Limitations 2 HDD per blade
Acquisition cost - 0
Lead Time to operation -
Power Needs - 0
Running costs - Approx 4K USD/month (first year)