IPv6 B-release status 1. Project name IPv6

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues Green

3.Name of person providing status Bin Hu (bh526r@att.com)

4.a link to your Jira tasks (filtered on R2) https://jira.opnfv.org/issues/?jql=project%20%3D%20IPVSIX%20AND%20labels%20%3D%20R2

5.a link to your Jira dashboard https://jira.opnfv.org/browse/IPVSIX/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel

6.a statement of your progress at linking cross project dependencies in Jira We have given our input to tests (https://etherpad.opnfv.org/p/testing_requests_for_b_release) as well as CI / Jenkins integration. Dependency on CI was created (OCTO-135) and linked by IPVSIX-7. We are waiting for feedback and further joint work planning from tests. Documentation project also created 2 tasks dependent on IPv6 - IPv6 Configuration Guide (IPVSIX-29) for DOCS-40, and IPv6 User Guide (IPVSIX-30) for DOCS-41.

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) We have our detailed planning done and in Jira (IPVSIX-18), and 3 tasks are defined in Jira too (IPVSIX-23, IPVSIX-24 and IPVSIX-25) for Sprint 1.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints High level planning is complete. All epics are identified and created in Jira (IPVSIX-6, IPVSIX-7, IPVSIX-9, IPVSIX-12, IPVSIX-13, IPVSIX-14 and IPVSIX-27) for future sprints.

9.a statement about any issues you have No current issue

10.how & when you will finish getting your tasks & dependencies into Jira if not complete Tasks and dependencies are done. We’re working on organizing our tasks into sprints.

11.how and when you will get ready to start development for Brahmaputra if not ready now We already started, and completed 12 tasks so far.

12.a statement summarizing your project risk analysis & planning status Low risk and on track