==== Agenda of IPv6 Project Meeting on October 02, 2015 ==== | ==== Agenda of IPv6 Project Meeting on October 02, 2015 ==== | ||
+ | * Roll call | ||
+ | * Admin Update | ||
+ | * B Release Planning Update | ||
+ | * Requirement on Genesis, CI, FuncTest or anything else? | ||
+ | * [[https://etherpad.opnfv.org/p/testing_requests_for_b_release| Testing Requirement for B Release]] | ||
+ | * JIRA: IPVSIX-10 Create timeline of milestones of IPv6, and aligned with B release | ||
+ | * **08/18/2015: B Release Milestone A** | ||
+ | * **08/18/2015: B Release Milestone B** | ||
+ | * **09/25/2015: B Release Milestone C** | ||
+ | * 09/25: Revised PoC 1 Diagram completion | ||
+ | * 10/09: Sprint C-1: Gap analysis with ODL completion (IPVSIX-18) | ||
+ | * 10/15: Sprint C-2: Test Plan completion (IPVSIX-14) | ||
+ | * 10/30: Decision on Snapshot image or Metadata (latency issue) | ||
+ | * 11/15: Sprint C-3: Jenkins integration completion (IPVSIX-7) | ||
+ | * 11/30: Sprint C-4: Test completion (IPVSIX-27) | ||
+ | * **12/01/2015: B Release Milestone D** | ||
+ | * **01/05/2016: B Release Milestone E** | ||
+ | * **02/02/2016: B Release Target Date** | ||
+ | * Other update of B Release | ||
+ | * [[https://etherpad.opnfv.org/p/Brahmaputra_Release_Weekly_Project_Status| B Release Weekly Project Status]] | ||
+ | * Jira issue status | ||
+ | * Gerrit repo status | ||
+ | * B Release Tasks Update | ||
+ | * Epic: JIRA IPVSIX-12 IPv6 Support / Gap Analysis with ODL | ||
+ | * Story: JIRA IPVSIX-19 Revision of PoC 1 Diagram | ||
+ | * Task: JIRA IPVSIX-20: Sridhar adds how IPv4 routing happens for VMs (Tenant B) in the diagram | ||
+ | * Task: JIRA IPVSIX-21: Sridhar reviews the setup instructions, and see if any change is needed to support dual-stack Service VM vRouter. | ||
+ | * Task: JIRA IPVSIX-22: Sridhar modifies diagram to use external IPv6 router for the setup of OS+ODL | ||
+ | * Story: JIRA IPVSIX-18 Gap Analysis Wiki of IPv6 on ODL (Sprint C-1) | ||
+ | * Task: JIRA IPVSIX-23: Iben creates Spirent VCTLab accounts for Sridhar, Meenakshi, and Prakash | ||
+ | * Task: JIRA IPVSIX-24: Sridhar and Meenakshi set up Lithium SR1 integration | ||
+ | * Task: JIRA IPVSIX-25: Sridhar and Meenakshi continue ODL gap analysis based on this setup. | ||
+ | * Epic: JIRA IPVSIX-13 Metadata Methodology / cloud.init() | ||
+ | * Sridhar has done it. Update of further experiment from all | ||
+ | * Epic: JIRA IPVSIX-14 Test methodoloy, test case development and testing related tasks (Sprint C-2) | ||
+ | * Multisite IPv6 Community Lab and CI Integration Update (Iben) | ||
+ | * Epic: JIRA: IPVSIX-7 Experiment and document instructions on Jenkins integration (Sprint C-3) | ||
+ | * Dependent on JIRA OCTO-135 | ||
+ | * Epic: JIRA: IPVSIX-9 Setup IPv6 in OPNFV Community Test Labs | ||
+ | * Epic: JIRA: IPVSIX-27 Test Completion using FuncTest or other test tools integration (Sprint C-4) | ||
+ | * Epic:JIRA: IPVSIX-6 Propose Metadata structure of IPv6 ISO | ||
+ | * Progress update from Prakash and Iben in terms of brown field experience, and vPING and vLOOP. | ||
+ | * Story: JIRA IPVSIX-29 Create an IPv6 chapter for the configuration guide | ||
+ | * Required by DOCS-40 | ||
+ | * Story: JIRA IPVSIX-30 Create an IPv6 user guide chapter for the Brahmaputra user guide | ||
+ | * Required by DOCS-41 | ||
+ | * Next Step | ||
* AOB | * AOB | ||