Line 1: Line 1:
 +1. Project name
 +
 +Moon
 +
 +2. Project status indicator for milestone C readiness:
 +
 +GREEN
 +
 +3.Name of person providing status
 +
 +Ruan HE<​ruan.he@orange.com>​
 +
 +4.a link to your Jira tasks (filtered on R2)
 +
 +https://​jira.opnfv.org/​browse/​MOON-22?​jql=project%20%3D%20MOON%20AND%20resolution%20%3D%20Unresolved%20AND%20issuetype%20%3D%20Task%20ORDER%20BY%20priority%20DESC
 +
 +5.a link to your Jira dashboard
 +
 +https://​jira.opnfv.org/​browse/​MOON/?​selectedTab=com.atlassian.jira.jira-projects-plugin:​issues-panel
 +
 +6.a statement of your progress at linking cross project dependencies in Jira
 +
 +We’ve contacted Multi-side to work on an identity federation solution.
 +
 +We’ve get feedback from the security working group.
 +
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
 +
 +The first release was finished last year, before entering OPNFV.
 +
 +From this year, we work on the release 2 of Moon, which is a stable version (https://​jira.opnfv.org/​browse/​MOON-2).
 +
 +We plan to start release 3 (https://​jira.opnfv.org/​browse/​MOON-22) from October 2015 which can be integrated to the Release C of OPNFV>
 +
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints
 +
 +We are now working on a new release (R2) of Moon. It’s objective is to provide a stable version but only applicable for OpenStack. From October, we will start release 3 of Moon which extends its scope to OpenDaylight. This is the reason why we believe Moon contribution will be integrated in Realse C of OPNFV.
 +
 +9.a statement about any issues you have
 +
 +No issues at this point.
 +
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete
 +
 +All the tasks and dependencies have been entered in Jira..
 +
 +11.how and when you will get ready to start development for Brahmaputra if not ready now
 +
 +Development for B-release has already begun (outside Jira) but we believe that our contribution will be integrated in release C.
 +
 +12.a statement summarizing your project risk analysis & planning status
 +
 +Low risk and on track so far.
  