1. Project name
Multisite
2.Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues Green
3. Name of person providing status
Chaoyi Huang
4.a link to your Jira tasks (filtered on R2), https://jira.opnfv.org/browse/MULTISITE-13?jql=project%20%3D%20MULTISITE%20AND%20labels%20%3D%20R2
5.a link to your Jira dashboard https://jira.opnfv.org/browse/MULTISITE/?selectedTab=com.atlassian.jira.jira-projects-plugin:issues-panel
6.a statement of your progress at linking cross project dependencies in Jira No dependency to other project in OPNFV
7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) https://jira.opnfv.org/browse/MULTISITE-11?jql=project%20%3D%20MULTISITE%20AND%20%22Epic%20Name%22%20~%20%22multisite%20sprint1%22
8.a statement of your readiness (high level planning complete & in Jira) for future sprints https://jira.opnfv.org/browse/MULTISITE-12?jql=project%20%3D%20MULTISITE%20AND%20%22Epic%20Name%22%20~%20%22multisite%20sprint2%22
9.a statement about any issues you have https://jira.opnfv.org/browse/MULTISITE-13?jql=project%20%3D%20MULTISITE
10.how & when you will finish getting your tasks & dependencies into Jira if not complete Sprint1 finished on Oct.25, Sprint2 on Nov.30, 2 months for buffer.
11.how and when you will get ready to start development for Brahmaputra if not ready now Sprint1 finished on Oct.25, Sprint2 on Nov.30, 2 months for buffer.
12.a statement summarizing your project risk analysis & planning status The output of OPNFV requirement project for sprint1&sprint2 will be ok, but BP/bug approve and fix progress will be up to OpenStack.