 +Project name 
 +OVSNFV
 +
 +2. Project status indicator for milestone C readiness: Green/​Yellow/​Red;​ GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues ​
 +Green 
 +
 +3.Name of person providing status ​
 +Billy O’Mahony
 +
 +4.a link to your Jira tasks (filtered on R2) 
 +https://​jira.opnfv.org/​issues/?​jql=project%20%3D%20OVSNFV%20AND%20status%20%3D%20Open%20ORDER%20BY%20priority%20DESC
 +
 +5.a link to your Jira dashboard ​
 +https://​jira.opnfv.org/​browse/​OVSNFV/?​selectedTab=com.atlassian.jira.jira-projects-plugin:​issues-panel
 +
 +6.a statement of your progress at linking cross project dependencies in Jira 
 +Stories OVSNFV-7, OVSNFV-8, OVSNFV-9 have been created to track these tasks.
 +
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) ​
 +Awaiting Jira permissions to create sprints (Team member with permissions is on annual leave)
 +
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints ​
 +First sprint is ready and remaining sprints at a high level. Awaiting permissions to enter on Jira.
 +
 +9.a statement about any issues you have 
 +None
 +
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete ​
 +Jira is complete for Sprint 1.
 +
 +11.how and when you will get ready to start development for Brahmaputra if not ready now 
 +Development has already started.
 +
 +12.a statement summarizing your project risk analysis & planning status ​
 +Low risk and on track so far.
  