This shows you the differences between two versions of the page.
| — |
pharos_milestone_c_report [2015/09/28 22:15] (current) Debra Scott created |
||
|---|---|---|---|
| Line 1: | Line 1: | ||
| + | 1.Project name | ||
| + | Pharos | ||
| + | |||
| + | 2.Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
| + | YELLOW | ||
| + | |||
| + | 3.Name of person providing status | ||
| + | Trevor Cooper | ||
| + | |||
| + | 4.a link to your Jira tasks (filtered on R2), | ||
| + | https://jira.opnfv.org/browse/PHAROS-59?jql=project%20%3D%20PHAROS%20and%20labels%20%3D%20R2 | ||
| + | |||
| + | 5.a link to your Jira dashboard | ||
| + | https://jira.opnfv.org/browse/PHAROS/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel | ||
| + | |||
| + | 6.a statement of your progress at linking cross project dependencies in Jira | ||
| + | Projects requiring lab resources … Pharos needs to address all test and development infrastructure needs which have not been fully stated yet | ||
| + | · CI has a dependency on Pharos for resources … we need to understand these requirements fully re. capacity | ||
| + | |||
| + | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
| + | · Epics and stories are substantially in Jira, some stories still to be added | ||
| + | · Scope has to be finalized and all tasks need to be assigned | ||
| + | |||
| + | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
| + | High level plan is reflected in Jira … we will organize around activities | ||
| + | |||
| + | 9.a statement about any issues you have | ||
| + | Resourcing … we need more heads/hands to own various activities. | ||
| + | |||
| + | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
| + | End of next week plan to have tasks assigned where possible with gaps clearly defined | ||
| + | |||
| + | 11.how and when you will get ready to start development for Brahmaputra if not ready now n.a. | ||
| + | |||
| + | 12. Risks Resourcing … need help from all Pharos committer and lab owners. Scope may need to change depending on resource availability. | ||