+ | 1.Project name | ||
+ | Pharos | ||
+ | |||
+ | 2.Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
+ | YELLOW | ||
+ | |||
+ | 3.Name of person providing status | ||
+ | Trevor Cooper | ||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2), | ||
+ | https://jira.opnfv.org/browse/PHAROS-59?jql=project%20%3D%20PHAROS%20and%20labels%20%3D%20R2 | ||
+ | |||
+ | 5.a link to your Jira dashboard | ||
+ | https://jira.opnfv.org/browse/PHAROS/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel | ||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira | ||
+ | Projects requiring lab resources … Pharos needs to address all test and development infrastructure needs which have not been fully stated yet | ||
+ | · CI has a dependency on Pharos for resources … we need to understand these requirements fully re. capacity | ||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
+ | · Epics and stories are substantially in Jira, some stories still to be added | ||
+ | · Scope has to be finalized and all tasks need to be assigned | ||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
+ | High level plan is reflected in Jira … we will organize around activities | ||
+ | |||
+ | 9.a statement about any issues you have | ||
+ | Resourcing … we need more heads/hands to own various activities. | ||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
+ | End of next week plan to have tasks assigned where possible with gaps clearly defined | ||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now n.a. | ||
+ | |||
+ | 12. Risks Resourcing … need help from all Pharos committer and lab owners. Scope may need to change depending on resource availability. | ||