User Tools

Site Tools


pharos_milestone_c_report

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

pharos_milestone_c_report [2015/09/28 22:15] (current)
Debra Scott created
Line 1: Line 1:
 +1.Project name
 +Pharos
 + 
 +2.Project status indicator for milestone C readiness: Green/​Yellow/​Red;​ GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
 +YELLOW
 + 
 +3.Name of person providing status
 +Trevor Cooper
 + 
 +4.a link to your Jira tasks (filtered on R2),
 +https://​jira.opnfv.org/​browse/​PHAROS-59?​jql=project%20%3D%20PHAROS%20and%20labels%20%3D%20R2
 + 
 +5.a link to your Jira dashboard
 + ​https://​jira.opnfv.org/​browse/​PHAROS/?​selectedTab=com.atlassian.jira.jira-projects-plugin:​summary-panel
 + 
 +6.a statement of your progress at linking cross project dependencies in Jira
 +Projects requiring lab resources … Pharos needs to address all test  and development infrastructure needs which have not been fully stated yet
 +·         CI has a dependency on Pharos for resources … we need to understand these requirements fully re. capacity
 + 
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
 +·         Epics and stories are substantially in Jira, some stories still to be added
 +·         Scope has to be finalized and all tasks need to be assigned
 + 
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints
 +High level plan is reflected in Jira … we will organize around activities
 + 
 +9.a statement about any issues you have
 +Resourcing … we need more heads/hands to own various activities.
 + 
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete
 +End of next week plan to have tasks assigned where possible with gaps clearly defined
 + 
 +11.how and when you will get ready to start development for Brahmaputra if not ready now n.a.
 + 
 +12.  Risks        Resourcing … need help from all Pharos committer and lab owners. Scope may need to change depending on resource availability.
  
pharos_milestone_c_report.txt · Last modified: 2015/09/28 22:15 by Debra Scott