This shows you the differences between two versions of the page.
— |
promise_milestone_c_report [2015/09/28 22:20] (current) Debra Scott created |
||
---|---|---|---|
Line 1: | Line 1: | ||
+ | 1. Project name | ||
+ | PROMISE | ||
+ | 2. Project status indicator for milestone C readiness: | ||
+ | GREEN | ||
+ | |||
+ | 3.Name of person providing status | ||
+ | Peter Lee <plee@clearpathnet.com> | ||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2) | ||
+ | https://jira.opnfv.org/issues?filter=10628 | ||
+ | |||
+ | 5.a link to your Jira dashboard | ||
+ | https://jira.opnfv.org/secure/Dashboard.jspa?selectPageId=10609 | ||
+ | https://jira.opnfv.org/secure/RapidBoard.jspa?rapidView=51&view=planning | ||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira | ||
+ | Completed providing cross project linkage with GENESIS-55 and Functest | ||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
+ | Epics, Stories, and Tasks have been identified and planned for Sprint-1 | ||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
+ | High-level planning for future sprints has been completed. Promise project will have 8 primary EPICs and 4 Sprints leading up to the B-release. Each Sprint will be 4 week in duration (one sprint every month). There will be additional planning prior to each Sprint iteration in order to identify any additional Stories/Tasks before commencement. | ||
+ | |||
+ | 9.a statement about any issues you have | ||
+ | There are no major issues at this time, other than reserving time and resources for the project (no pun intended…) | ||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
+ | The main Stories/Tasks for Sprint-1 are complete. We will likely define additional Sub-Tasks as necessary as assignments are delegated next week. | ||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now | ||
+ | Development for B-release has already begun (outside Jira) but we will be commencing the Jira based Sprint-1 on October 1st. | ||
+ | |||
+ | 12.a statement summarizing your project risk analysis & planning status | ||
+ | Risk level is low. There are no blocker dependencies from other projects/components and current planning indicates B-release readiness along the established timelines. Primary risk is around integration with a community NFVI lab to ensure consistent deployment and functionality verification. |