User Tools

Site Tools


releases:brahmaputra:release_plan:escalator_milestone_d_report

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
releases:brahmaputra:release_plan:escalator_milestone_d_report [2015/11/26 12:17]
Jie Hu
releases:brahmaputra:release_plan:escalator_milestone_d_report [2015/11/26 12:35] (current)
Jie Hu
Line 17: Line 17:
  
 6. List/​describe your progress to date?  6. List/​describe your progress to date? 
-Requirement document is ready but still in discussion.  ​+First version or Requirement document is ready for review.  ​
  
 7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) 7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.)
-Complete the requirement document ​and gap analysis report.+Complete the requirement document.
  
 8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/​Yellow/​Red 8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/​Yellow/​Red
-YELLOW+Yellow
  
 9. List any serious or blocking issues that are impeding progress on your project: 9. List any serious or blocking issues that are impeding progress on your project:
-NA+Less people, less contributions during the Long Christmas holiday.