This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
releases:brahmaputra:release_plan:onosfw_milestone_d_report [2015/11/26 14:17] Ashlee Young |
releases:brahmaputra:release_plan:onosfw_milestone_d_report [2015/12/01 01:48] (current) Wei Su |
||
---|---|---|---|
Line 12: | Line 12: | ||
6. List/describe your progress to date? | 6. List/describe your progress to date? | ||
- | We are Feature Complete and are currently working on our installers for Apex, Compass, Fuel, and JuJu. All of the installer work is underway as parallel sub-projects. We are also finishing up our automated, build, package, deploy, and test capabilities; so that we can do our own regression testing. We are also doing stability/bug fixing, along with optimizations. | + | We are Feature Complete and are currently working on our installers for Apex, Compass4NFV, Fuel, and JOID. All of the installer work is underway as parallel sub-projects. We are also finishing up our automated, build, package, deploy, and test capabilities; so that we can do our own regression testing. We are also doing stability/bug fixing, along with optimizations. [[https://jira.opnfv.org/secure/ConfigureReport.jspa?projectOrFilterId=project-10311&statistictype=resolution&selectedProjectId=10311&reportKey=com.atlassian.jira.plugin.system.reports%3Apie-report&Next=Next|ONOSFW B Release Status Tracking]] |
7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) | 7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) |