This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
releases:brahmaputra:release_plan:pharos_milestone_d_report [2015/12/01 06:43] Trevor Cooper |
releases:brahmaputra:release_plan:pharos_milestone_d_report [2015/12/01 06:48] (current) Trevor Cooper |
||
---|---|---|---|
Line 20: | Line 20: | ||
7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) | 7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) | ||
- | Complete MAAS Pilot | + | * Complete MAAS Pilot |
- | Machine and human readable templates | + | * Machine and human readable templates |
- | Support for LF infra | + | * Need training for volunteers to support for LF infrastructure |
+ | * Help all labs to be Pharos compliant | ||
+ | * Some labs while available still need to publish developer access process and guides | ||
+ | * Some labs are not yet setup under Jenkins control | ||
8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red | 8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red |