Line 17: Line 17:
  
 6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n 6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n
-We have not been using Jira for lab ops / issues ... working on a scheme to implement this as lab management with emails is unmanageable. Lab resource allocation and status is available here https://​wiki.opnfv.org/​pharos_rls_b_labs+We have not been using Jira for lab ops / issues ... we are working on a scheme to implement this. Lab resource allocation and status is available here https://​wiki.opnfv.org/​pharos_rls_b_labs
  
 7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users? y/n 7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users? y/n
-n+Jira tasks are not explicitly prioritized ​
  
 8. All known open critical Jira Tickets have been closed or have a workaround in place? y/n 8. All known open critical Jira Tickets have been closed or have a workaround in place? y/n
 n n
-Critical items are ops related+Most critical ​are operational issues ... providing resources and support for all testing needs. Once scenarios are agreed we will review a plan for shared resources. ​
  
 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n
-Need to scrub Jira tickets to allocate future ​milestones ​or close +
 +Need to scrub Jira tickets to review/​allocated deferred/​later ​milestones ​
  
 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release?
 No, documentation needs updating and some new documents need to be generated. Planning to work on documentation next week. No, documentation needs updating and some new documents need to be generated. Planning to work on documentation next week.