releases:brahmaputra:release_plan:qtip_milestone_e_report [2015/12/17 19:44] Debra Scott created |
releases:brahmaputra:release_plan:qtip_milestone_e_report [2016/01/05 19:59] (current) Vikram Dham |
||
|---|---|---|---|
| Line 2: | Line 2: | ||
| 1. Has your test framework been executed against a deployed OPNFV platform? | 1. Has your test framework been executed against a deployed OPNFV platform? | ||
| + | |||
| + | |||
| + | Yes: Tested against Fuel. (Was earlier tested against Foreman) | ||
| + | Would be testing on Apex, Compass and JOID in the coming week | ||
| + | |||
| 2. Has your deploy tool been executed in more than one Pharos lab? | 2. Has your deploy tool been executed in more than one Pharos lab? | ||
| + | |||
| + | No: Only tested in the Dell OPNFV lab. | ||
| + | Would be testing it out in other labs during the course of the coming week. | ||
| + | |||
| 3. Have your test framework and test cases been run against more than one deployment tool? | 3. Have your test framework and test cases been run against more than one deployment tool? | ||
| + | |||
| + | No. Only tested against Fuel as of yet. | ||
| + | |||
| 4. Do you have all target Brahmaputra test cases available in your test suites? | 4. Do you have all target Brahmaputra test cases available in your test suites? | ||
| + | |||
| + | Yes. | ||
| + | |||
| 5. Is your test framework able to be repeated on the same infrastructure at least 4 consecutive times without failures? Does it meet the agreed upon criteria of "stable"? | 5. Is your test framework able to be repeated on the same infrastructure at least 4 consecutive times without failures? Does it meet the agreed upon criteria of "stable"? | ||
| + | |||
| + | Yes. | ||
| + | |||
| 6. Have all known test issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? | 6. Have all known test issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? | ||
| + | |||
| + | |||
| + | Test issues are being documented as part of the QTIP documentation. | ||
| + | In case there are issues that arise later, they would be listed on the wiki page. | ||
| + | |||
| 7. Are all known issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users? | 7. Are all known issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users? | ||
| + | |||
| + | Yes. | ||
| + | |||
| 8. Do all known critical Jira Tickets have a workaround in place? | 8. Do all known critical Jira Tickets have a workaround in place? | ||
| + | |||
| + | Most Critical Jira Tickets till date have been resolved. Cirtical Jira Tickets may pop up in the coming days when testing with other installers such as Apex. | ||
| + | |||
| 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)? | 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)? | ||
| + | |||
| + | Yes. Deferred-fix in later release (such as integration with vswitchperf ) | ||
| + | |||
| 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? | 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? | ||
| + | |||
| + | Documentation has been started. Initial templates submitted. Would be working on it till mid January. | ||