 +1. Project name
 +Releng
 +
 +2. Project status indicator for milestone C readiness: Green/​Yellow/​Red;​ GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
 + Green
 +
 +3.Name of person providing status
 + Fatih Degirmenci
 +
 +4.a link to your Jira tasks (filtered on R2)
 + ​https://​jira.opnfv.org/​issues/?​filter=10607
 +
 +5. a link to your Jira dashboard
 + ​https://​jira.opnfv.org/​secure/​Dashboard.jspa?​selectPageId=10607
 +(Kanban board: https://​jira.opnfv.org/​secure/​RapidBoard.jspa?​rapidView=13)
 +
 +6.a statement of your progress at linking cross project dependencies in Jira
 + ​Releng project has dependencies towards projects listed below.
 +  Pharos for hardware/​lab resources, dashboard, booking system.
 +  Octopus for CI pipeline descriptions and processes.
 +   ​Functest and Yardstick for test result reporting/​dashboard implementation.
 +   There are implicit dependencies towards Genesis, Installer projects, and projects that produce artifacts that are going to be integrated into CI.
 +   These dependencies are not visible as of yet since they are still in progress by Genesis project so they have not been linked as dependencies to Releng.
 +   
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
 + ​Ready. 4 Epics and Stories under these Epics have been identified. Development work has already been started.
 +
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints
 + ​Ready. Releng does not work in Scrum so no sprints defined.
 +
 +9.a statement about any issues you have
 + Lack of hardware resources.
 +
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete
 + ​Backlog in Jira is ready.
 +
 +11.how and when you will get ready to start development for Brahmaputra if not ready now
 + ​Ready. Development work has already been started.
 +
 +12.a statement summarizing your project risk analysis & planning status
 + ​Pharos and Octopus projects have high impacts on Releng so any delay in the these projects will risk Releng for progressing further.
 +Apart from the explicit dependencies listed above, the high number of Brahmaputra participating projects and the late requests that might arrive from these projects have potential to increase the risk.
 +Needs that might arise from the projects that produce artifacts, Genesis, and Installer projects also have high impact on Releng when it comes to automation/​integration effort.
  