1.Project name:

Resource Scheduler (Conductor)

2.Project status indicator for milestone C readiness:

Green

3.Name of person providing status:

Rex Lee (limingjiang@huawei.com)

4.a link to your Jira tasks (filtered on R2):

https://jira.opnfv.org/issues/?jql=project%20%3D%20CONDUCTOR%20AND%20labels%20%3D%20R2

5.a link to your Jira dashboard:

https://jira.opnfv.org/browse/CONDUCTOR/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel

6.a statement of your progress at linking cross project dependencies in Jira.

We have some relations with MOVIE on API & Configuration filter.

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile).

Yes we have started work on the typical use cases, and update the status in jira.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints.

We have create 2 main epics for us to track the process in Jira.

9.a statement about any issues you have.

Currently working on typical use cases and propose BPs to OpenStack Nova.

10.how & when you will finish getting your tasks & dependencies into Jira if not complete?

Already finish.

11.how and when you will get ready to start development for Brahmaputra if not ready now?

Have started.

12.a statement summarizing your project risk analysis & planning status.

Bps have better to be proposed to OpenStack Nova before Tokyo Summit.

rs_milestone_c_report.txt · Last modified: 2015/09/28 22:26 by Debra Scott