 +1. Project name 
 +Software Fastpath Service Quality Metrics-SQFM
 +
 +2. Project status indicator for milestone C readiness: Green/​Yellow/​Red;​ GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues
 +Green
 +
 +3.Name of person providing status ​
 +Maryam Tahhan maryam.tahhan@intel.com
 +
 +4.a link to your Jira tasks (filtered on R2) 
 +https://​jira.opnfv.org/​issues/?​jql=project%20%3D%20SFQM%20AND%20labels%20%3D%20R2
 +
 +5.a link to your Jira dashboard ​
 +https://​jira.opnfv.org/​secure/​RapidBoard.jspa?​rapidView=57&​selectedIssue=SFQM-6
 +
 +6.a statement of your progress at linking cross project dependencies in Jira
 +We don’t have any cross project dependencies.
 +
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)
 +We have our detailed planning done and in Jira, and 4 features are defined in Jira too (SFQM-3 to SFQM-6) for Sprint 1.
 +
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints
 +High level planning is complete. All epics are identified and created in Jira (SFQM-2)
 +
 +9.a statement about any issues you have 
 +No current issues
 +
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete
 +Tasks and dependencies are done.
 +
 +11.how and when you will get ready to start development for Brahmaputra if not ready now
 +We already started, and plan on submitting all of our 1st draft patches to DPDK next week.
 +
 +12.a statement summarizing your project risk analysis & planning status
 +Low risk and on track
  