vsperf_milestone_c_report [2015/09/28 22:38] (current) Debra Scott created |
||
---|---|---|---|
Line 1: | Line 1: | ||
+ | 1. Project name | ||
+ | VSPERF | ||
+ | |||
+ | 2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues | ||
+ | Green | ||
+ | |||
+ | 3.Name of person providing status | ||
+ | Maryam Tahhan maryam.tahhan@intel.com | ||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2) | ||
+ | https://jira.opnfv.org/issues/?jql=project%20%3D%20VSPERF%20AND%20labels%20%3D%20R2 | ||
+ | |||
+ | 5.a link to your Jira dashboard | ||
+ | https://jira.opnfv.org/secure/RapidBoard.jspa?rapidView=43&view=planning&selectedIssue=VSPERF-106&epics=visible | ||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira | ||
+ | We depend on RELENG and Octopus, but we will be taking on the tasks to resolve these dependencies. | ||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) | ||
+ | We have our detailed planning done and in Jira, and detailed sprint 1 and themes for consequent sprints. | ||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints | ||
+ | High level planning is complete. All epics are identified and created in Jira (https://jira.opnfv.org/browse/VSPERF-75) | ||
+ | |||
+ | 9.a statement about any issues you have | ||
+ | No current issues | ||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete | ||
+ | Tasks and dependencies are done. | ||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now | ||
+ | We already started, and plan on continuing to execute the planned sprints. | ||
+ | |||
+ | 12.a statement summarizing your project risk analysis & planning status | ||
+ | Low risk and on track | ||