Line 1: Line 1:
 +1. Project name 
 +Compass4nfv
 +
 +2. Project status indicator for milestone C readiness: Green/​Yellow/​Red;​ GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues ​
 +Green 
 +
 +3.Name of person providing status ​
 +Weidong Shao, with assistance from Chen Shuai, and Chi Gang(Justin)
 +
 +4.a link to your Jira tasks (filtered on R2) 
 +https://​jira.opnfv.org/​issues/?​jql=project%20%3D%20COMPASS%26labels%3DR2
 +
 +5.a link to your Jira dashboard ​
 +https://​jira.opnfv.org/​browse/​COMPASS/?​selectedTab=com.atlassian.jira.jira-projects-plugin:​summary-panel
 +
 +6.a statement of your progress at linking cross project dependencies in Jira 
 +Compass4nfv is an installer project under Genesis. Currently working with other Genesis committers on Jira reviews.
 + 
 +7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile) ​
 +Not an agile mode, but the next major milestone in 10/30 for support of deploying OpenStack Liberty, and for supporting installation of Compass on a vanilla OS host (in addition to ISO-based install)
 +
 +8.a statement of your readiness (high level planning complete & in Jira) for future sprints ​
 +Will work with Genesis, and other projects that have requirements on Genesis. There are certain uncertainties in this area as the Genesis requirements are still under review.
 +
 +9.a statement about any issues you have 
 +There are some risks in the cross-project dependencies,​ due to the nature of installer, with support of many different upstream projects.
 +
 +
 +10.how & when you will finish getting your tasks & dependencies into Jira if not complete ​
 +Will map new approved Genesis to our Jira as they come up. 
 +
 +11.how and when you will get ready to start development for Brahmaputra if not ready now 
 +We are already in active development and have a working foundation (that supports OpenStack kilo/ODL lithium and ONOS Drake)
 +
 +12.a statement summarizing your project risk analysis & planning status ​
 +Risk is low. Overall status is Green. ​
  