policy_test_milestone_c_report

Project name

PolicyTest

2. Project status indicator for milestone C readiness: Green/Yellow/Red; GREEN = on track; YELLOW = working minor issues to get back on track; RED = offtrack with major issues

YELLOW

3.Name of person providing status Keith Burns

4.a link to your Jira tasks (filtered on R2)

https://jira.opnfv.org/browse/POLICYTEST-5?filter=-2

5.a link to your Jira dashboard

https://jira.opnfv.org/secure/RapidBoard.jspa?rapidView=65&selectedIssue=POLICYTEST-1

6.a statement of your progress at linking cross project dependencies in Jira In progress: RELENG-37, GENESIS-57, GENESIS-58

7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile)

Still a nascent project. Only got JIRA access this week. Also just got correct permissions for Gerrit established this week.

8.a statement of your readiness (high level planning complete & in Jira) for future sprints

We do not plan to organize around sprints.

9.a statement about any issues you have

Porting of ODL GBP Jenkins/Robot environment to OPNFV environment. Don't anticipate anything horrible, just a learning curve.

10.how & when you will finish getting your tasks & dependencies into Jira if not complete Still trying to co-ordinate first team meeting of committers to review JIRA. May have to iron out any access-rights they may have, but anticipate having this complete in a week, once we get feedback on expectations from cross-project JIRA tickets

11.how and when you will get ready to start development for Brahmaputra if not ready now

First PolicyTest environment is based on an existing complete GBP+SFC environment found at: https://wiki.opendaylight.org/view/Group_Based_Policy_%28GBP%29/Consumability/Demo

12.a statement summarizing your project risk analysis & planning status

With the current scope we do not anticipate any significant risk of delivery for Brahmaputra. Having said that, our planning status is nascent, but since we are leveraging a known working environment based on ODL Stable/Lithium, the issues are more porting than technical/developmental

policy_test_milestone_c_report.txt · Last modified: 2015/09/28 22:16 by Debra Scott