Apex Milestone D Report

1. If you have code are features frozen? y/n/na - y main features are frozen. Some configuration differences or dependencies may change due to Genesis voting on common requirements.

2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? y/n/na - y

3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite) y/n/na - na

4. If you require post-install processing have you consulted with CI (Octopus), CD (Releng), and/or companion test projects (functest, yardstick, etc) regarding scripts you may need to provide such as for install, set-env, run-test, clean-env? na

5. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? y/n/na - na, but have delivered our first draft of installer documentation and release notes

6. List/describe your progress to date? Apex has OpenStack Liberty in HA building and deploying with ODL in a virtual environment on OPNFV CI.

7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.)

Major remaining items: 1. Baremetal support and CI work 2. Other SDN Controller support (OpenContrail, ONOS) 3. Integrating Ceph Storage 4. Ensuring we meet Genesis Requirements

8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red Green

9. List any serious or blocking issues that are impeding progress on your project: None