1. If you have code are features frozen? NA.

2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? NA.

3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite) N.

4. If you require post-install processing have you consulted with CI (Octopus), CD (Releng), and/or companion test projects (functest, yardstick, etc) regarding scripts you may need to provide such as for install, set-env, run-test, clean-env? NA.

5. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? DPACC is working on four deliverables, but none of them is ready for outside review now.

6. List/describe your progress to date? The team reached general agreement on DPACC architecture, use-cases and test spec. The team is now actively working on DPACC requirements and gap analysis.

7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) Clear up remaining issues with current documentation and port them to Gerrit.

8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red Red.

9. List any serious or blocking issues that are impeding progress on your project: