Fuel Milestone D Report

1. If you have code are features frozen? y/n/na - n - Collaborative project participation feature freeze will happen December 17, as was always communicated sinse September - please see the work-package plan: https://wiki.opnfv.org/fuel_opnfv_b-wp

2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? y/n/na - y (unless any collaborative projects think otherwise, I think the question should have been put the otherway around)

3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite) y/n/na - n/a

4. If you require post-install processing have you consulted with CI (Octopus), CD (Releng), and/or companion test projects (functest, yardstick, etc) regarding scripts you may need to provide such as for install, set-env, run-test, clean-env? - n/a

5. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? y/n/na - n/a

6. List/describe your progress to date? - please see Jira for Fuel (https://jira.opnfv.org/secure/Dashboard.jspa?selectPageId=10608#)

7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) - Following the work-package plan set-out in September - see https://wiki.opnfv.org/fuel_opnfv_b-wp

8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red - Yellow2red Hard Codefreeze was always planned for WP4 Jan 15

9. List any serious or blocking issues that are impeding progress on your project: - You never asked about dependencies-, APIs etc.-, that our project rely on:

Genesis have yet not set the baseline for installers, nor have the Genesis/Releng/Functest/Pharos APIs been set 
so that installers, Releng, etc know how to build-, configure-, deploy and test according to required CI/CD 
requirements/permutation of features/collaboration project content - not in place! 