Milestone D Report

ID criteria status
1 If you have code are features frozen? y
2 If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? y
3 Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite) internal testcases OK, wait for companion feature project testcases
4 If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? na
5 List/describe your progress to date? Good progress on internal tasks, Test API will be frozen in time. Still open questions on the availability of production CI labs mandatory to start integrating on the different installers
6 Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) deploy Functest on the target CI labs (integration and installer adaptation foreseen , finalize ODL test suite code, finalize Tempest/rally test suites, integrate all the feature projects, create documentation, update test dashboard
7 How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Yellow (no visibility on availability of the CI production labs, light visibility on feature test integration),
8 List any serious or blocking issues that are impeding progress on your project: availability of production labs