Line 13: | Line 13: | ||
6. List/describe your progress to date | 6. List/describe your progress to date | ||
- | // | + | |
* 75% of all Genesis requirements (represented as Jira tickets) have been processed by the Genesis team. The team works on resolving the last batch. | * 75% of all Genesis requirements (represented as Jira tickets) have been processed by the Genesis team. The team works on resolving the last batch. | ||
* Genesis closed the gate for new requirements for Brahmaputra on Nov/13/2015. | * Genesis closed the gate for new requirements for Brahmaputra on Nov/13/2015. | ||
- | // | + | |
7. Describe what you have remaining to do? | 7. Describe what you have remaining to do? | ||