1.If you have code are features frozen? Yes Codes are work in progress in ODL NEMO project upstream.

2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen? Yes NEMO Model APIs being used as part of the project and are frozen for Release B

3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite). Yes VPC with BOD & L3 VPN use cases are taken up and others are dropped from Release B.

4. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review? na Some of the documents are in ODL NEMO project upstream and will be included as part of Milestone E.

5. List/describe your progress to date? 80% of work is completed and we believe the progress is less than expected and we are trying to meet the timelines by Milestone E.

6. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.) We have narrowed the use cases to overcome the workload and will try meet the timelines in Milestone-R

7. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green We are going well on the ODL NEMO project, will mirror the code to OPNFV repository. And we will try best to narrow the scope to deliver on MOVIE by Jan 5th.

8. List any serious or blocking issues that are impeding progress on your project: Resource and Integration efforts with other projects is impediant to progress.