1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n | 1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n | ||
+ | No. We never run on Pharos lab. We have not integrated with CI framework. | ||
2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n | 2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n | ||
+ | No. | ||
3. Are your test cases all ready? y/n | 3. Are your test cases all ready? y/n | ||
+ | Yes. All tests have been completed locally. | ||
4. Are your test cases all passing? y/n | 4. Are your test cases all passing? y/n | ||
+ | No. The test cases have been created on Yardstick but have not been run yet. | ||
5. Do you feel you are prepared for code freeze on January 5th? y/n | 5. Do you feel you are prepared for code freeze on January 5th? y/n | ||
+ | Yes. Code freeze will be completed on 6th. Testing on test frame bed has not started yet. | ||
6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n | 6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n | ||
+ | All documentation is made available on wiki page. | ||
7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n | 7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n | ||
+ | Yes. We do not have any open known issues. | ||
8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n | 8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n | ||
+ | Yes | ||
9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n | 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n | ||
+ | Yes | ||
10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? | 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? | ||
+ | ?? |