1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n

 No. We never run on Pharos lab. We have not integrated with CI framework.

2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n

 No.

3. Are your test cases all ready? y/n

 Yes. All tests have been completed locally. 

4. Are your test cases all passing? y/n

 No. The test cases have been created on Yardstick but have not been run yet.

5. Do you feel you are prepared for code freeze on January 5th? y/n

 Yes. Code freeze will be completed on 6th. Testing on test frame bed has not started yet.

6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n

 All documentation is made available on wiki page.

7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n

 Yes. We do not have any open known issues.

8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n

 Yes

9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n

 Yes

10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release?

 ??
releases/brahmaputra/release_plan/nvf-kvm_milestone_e_report.txt · Last modified: 2016/01/06 21:19 by Raghuveer Reddy