 Parser Milestone E Report Parser Milestone E Report
  
-1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n+1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n  
 //no// //no//
 +
 2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n 2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n
 +
 //no// //no//
 +
 3. Are your test cases all ready? y/n 3. Are your test cases all ready? y/n
 +
 //yes// //yes//
 +
 4. Are your test cases all passing? y/n 4. Are your test cases all passing? y/n
 +
 //yes// //yes//
 +
 5. Do you feel you are prepared for code freeze on January 5th? y/n 5. Do you feel you are prepared for code freeze on January 5th? y/n
 +
 //all development related codes are able to be frozen on Jan 5th, there might be some testing code coming in the following 2 - 3 days// //all development related codes are able to be frozen on Jan 5th, there might be some testing code coming in the following 2 - 3 days//
 +
 6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n 6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n
 +
 //​Documentation are partially done, still lack of a general description document.// //​Documentation are partially done, still lack of a general description document.//
 +
 7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n 7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n
 +
 //yes// //yes//
 +
 8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n 8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n
 +
 //all are addressed but haven'​t been closed yet// //all are addressed but haven'​t been closed yet//
 +
 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n 9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n
 +
 //yes// //yes//
 +
 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release? 10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release?
 +
 //still working on a general description document// //still working on a general description document//