+ | 1.Project name: | ||
+ | Resource Scheduler (Conductor) | ||
+ | |||
+ | |||
+ | |||
+ | 2.Project status indicator for milestone C readiness: | ||
+ | |||
+ | Green | ||
+ | |||
+ | |||
+ | |||
+ | 3.Name of person providing status: | ||
+ | |||
+ | Rex Lee (limingjiang@huawei.com) | ||
+ | |||
+ | |||
+ | |||
+ | 4.a link to your Jira tasks (filtered on R2): | ||
+ | |||
+ | https://jira.opnfv.org/issues/?jql=project%20%3D%20CONDUCTOR%20AND%20labels%20%3D%20R2 | ||
+ | |||
+ | |||
+ | |||
+ | 5.a link to your Jira dashboard: | ||
+ | |||
+ | https://jira.opnfv.org/browse/CONDUCTOR/?selectedTab=com.atlassian.jira.jira-projects-plugin:summary-panel | ||
+ | |||
+ | |||
+ | |||
+ | 6.a statement of your progress at linking cross project dependencies in Jira. | ||
+ | |||
+ | We have some relations with MOVIE on API & Configuration filter. | ||
+ | |||
+ | |||
+ | |||
+ | 7.a statement of your readiness (detailed planning complete & in Jira) for your first sprint or first development cycle (if not agile). | ||
+ | |||
+ | Yes we have started work on the typical use cases, and update the status in jira. | ||
+ | |||
+ | |||
+ | |||
+ | 8.a statement of your readiness (high level planning complete & in Jira) for future sprints. | ||
+ | |||
+ | We have create 2 main epics for us to track the process in Jira. | ||
+ | |||
+ | |||
+ | |||
+ | 9.a statement about any issues you have. | ||
+ | |||
+ | Currently working on typical use cases and propose BPs to OpenStack Nova. | ||
+ | |||
+ | |||
+ | |||
+ | 10.how & when you will finish getting your tasks & dependencies into Jira if not complete? | ||
+ | |||
+ | Already finish. | ||
+ | |||
+ | |||
+ | |||
+ | 11.how and when you will get ready to start development for Brahmaputra if not ready now? | ||
+ | |||
+ | Have started. | ||
+ | |||
+ | |||
+ | |||
+ | 12.a statement summarizing your project risk analysis & planning status. | ||
+ | |||
+ | Bps have better to be proposed to OpenStack Nova before Tokyo Summit. |