This page includes project plans for the Models project per the C release planning page.
MS0 : Project planning
| Task | Estimated time/week | Contributors |
|---|---|---|
| Outreach to SDOs, Open Source projects, OPNFV projects | 2 hrs | Bryan |
| Model research/analysis | 2 hrs | Dan |
| Tools research/analysis (including MANO components) | 2 hrs | Dan |
| Use case development/testing | 2 hrs | Bryan |
MS1 : Planning complete
MS2 : Feature Code freeze
MS3: Installation Code freeze:
MS4: Test Code freeze
MS5: Integration ready:
MS6 : Release
| Must-Have Reqs | At-Risk Reqs |
|---|---|
| Use Cases | |
| Testbed | |
| Tests | |
| Release Notes |
| Working Plan Reqs | Outplan Reqs |
|---|---|
| Requirements Gap Analysis | |
| Draft Blueprints |
| Criticality | Project | Dependency Description |
|---|---|---|
| Must-Have | FuncTest | Incorporation of Models test scenarios C release functional tests, either as part of automated post-install tests, or as an on-demand test set. |
| Working Plan | TBD | Establishment of model-based feature priorities within the scope of OPNFV project. |
| Criticality | Project | Dependency Description |
|---|---|---|
| Must-Have | OpenStack | Latest stable release version, as basis for adding TBD components and testing |
| Must-Have | OpenDaylight | Latest stable release version, as basis for adding TBD components and testing |