Qtip Milestone D Report

1. If you have code are features frozen?

No, Addition of couple of networking test cases is still being discussed. Will be resolved by 12/7.

2. If you have api/s, files or other interfaces that other projects rely on to integrate with your project are they frozen?

NA

3. Are your test specifications frozen and provided to test projects? No additional use cases can be added to the release after this milestone (ie. feature projects have added the test cases for their project to the test team suite)

NA

4. If you require post-install processing have you consulted with CI (Octopus), CD (Releng), and/or companion test projects (functest, yardstick, etc) regarding scripts you may need to provide such as for install, set-env, run-test, clean-env?

No post install processing required.

5. If you have no code(e.g. documentation projects) - drafts of all deliverables exist and are ready for first review?

NA

6. List/describe your progress to date?

QTIP framework to run benchmarks is completed. Compute testcases completed Sotrage testcases completed Network test cases partially completed Jenkins job runs for QTIP on Dell Slave

7. Describe what you have remaining to do? (hint: You should only have completion of existing features and bug fixes to do. For test projects you will be developing remaining tests according to frozen specifications.)

Network testcases. Central Dashboard integration Ensuring QTIP results are pushed to OPNFV testing Data Running through Jenkins on other labs Final Consolidated reports Packaging of QTIP

8. How confident are you that you will be complete for Milestone E/code freeze on Jan 5? Green/Yellow/Red

Green-Yellow

9. List any serious or blocking issues that are impeding progress on your project: