1. Has your feature been executed on an OPNFV deployment in a Pharos lab? y/n
no

2. Have your test cases been run on the feature once deployed in a Pharos lab? y/n
no

3. Are your test cases all ready? y/n
have no test cases

4. Are your test cases all passing? y/n
have no test cases

5. Do you feel you are prepared for code freeze on January 5th? y/n
have no codes implement, just documentation

6. Have all known open issues (Jira tickets against your project) been documented and that documentation either integrated into the release or made available on a public page and pointed to through documents that are integrated into the release? y/n
not all

7. Are all known open issues (Jira Tickets) prioritized by severity of impact (critical, high, medium, low) to users?y/n
yes

8. All known open critical Jira Tickets have been closed or have a workaround in place?y/n
not all

9. Do all non-critical Jira Tickets have a planned disposition in place (ie. deferred-fix in later release or closed- won't fix)?y/n
yes

10. Is your documentation complete and checked in? If not, how do you plan to deliver it independent of the release?
not finished, need more work